The purpose of the Project is the construction of a sewer system and waste water treatment plant in Radecznica agglomeration, with the overall objective to improve public health, surface-water and ground water ecology. Reference is made to the application dated 10 April 2007 and any subsequent correspondence with the Focal Point. The completed Project shall include the following activities and results: • Construction of a wastewater treatment plant with the capacity of 250 m3/day ; • Construction of sewer network to connect 689 users • Project management and publicity. The Project Promoter is the Radecznica Commune. The Focal Point shall ensure that the Project Promoter provides at least 15 percent of the total estimated eligible Project cost.
Project details
Project info
Promoter
- Radecznica Commune
Period
2004-2009
Approval date
Project grant
Final project cost
890240.00€
Actual Cost
1108514.00€