The purpose of the Project is to establish and equip 12 perinatological centres in 9 cities throughout the country, with the overall objective of improving the health of premature babies born in the Czech Republic. Reference is made to the application dated 30 December 2007 and to any subsequent correspondence with the Focal Point. The completed Project shall include the following activities and results: - via a public tender process, purchase of 12 sets of equipment for the 12 perinatological centres and installation of equipment; - management and publicity The Project Promoter is the Charta 77 Foundation. The Focal Point shall ensure that the Project Promoter provides at least 15 percent of the total eligible Project costs.
Project details
Project info
Promoter
- The Charta 77 Foundation
Period
2004-2009
Approval date
Project grant
Final project cost
761657.00€
Actual Cost
896067.00€